How this calculator works
The maintenance scheduler builds a 12-month calendar from a library of about 60 generator tasks.
- Facility and frameworks. Your facility type preselects the rule sets that usually apply: NFPA 110 for everyone, plus Joint Commission and CMS for hospitals and surgery centers, CMS for nursing homes, Uptime Institute for data centers, and UFC for government sites. You can change the selection.
- Filtering. It keeps only tasks that match your fuel type (diesel, natural gas, or bi-fuel) and your selected frameworks, then adjusts for climate and installation type. Harsh climates or installations can move some tasks to monthly.
- Scheduling. Due dates count forward from your last service date. Older generators get shorter intervals.
- Score. The compliance score starts at 100 and drops for each overdue task, more for tasks that are further overdue.
The core NFPA 110 testing rules behind the schedule:
- Monthly exercise: at least 30 minutes, under load of at least 30% of nameplate or the manufacturer minimum exhaust temperature.
- Annual supplemental load test, only when monthly exercise can’t reach that load: 50% of nameplate for 30 minutes, then 75% for 60 minutes (2013 and later editions). The 2010 edition, which CMS and the Joint Commission enforce for health care, uses 25%, 50% and 75% for 30, 30 and 60 minutes.
- Level 1 systems, at least every 36 months: run for the class duration or 4 hours, whichever is less, at 30% or more of nameplate kW.
- An annual fuel quality test using ASTM methods. Polish fuel as test results indicate.
Where the schedule and these rules differ, the rules and your AHJ govern. Always follow your manufacturer’s manual.